Ministry of Public Works

Completion of Kifisos River rehabilitation between Posidonos Av. and Solomou str. (chainnage 0+000 - 0+700) at Moschato

Project Description

PROJECT Completion of Kifisos River rehabilitation between Posidonos Av. and Solomou str. (chainnage 0+000 – 0+700) at Moschato
OWNER Ministry of Public Works
PROJECT CONTRACTOR J/V PARNON S.A. – EUROPAIKI TECHNIKI S.A.
GEOTECHNICAL INVESTIGATION CONTRACTOR GEOCONSULT Ltd.
DATES OF GEOTECHNICAL INVESTIGATION November 1997 – January 1998

The project is located at the part of Kifisos River between the coastal Ethnarxou Makariou Avenue (chainnage 0+000) and Solomou str. (chainnage. 0+700), at the Moschato area. The project includes the rehabilitation of Kifisos River bed between chainnage 0+000 and chainnage 0+700.

Drilling 13 exploratory boreholes (9 on-shore and 4 inside the river) of a total length of approximately 350 m, with the corresponding laboratory tests, preparation of a factual and interpretive report and proposals for excavation retaining structures with sheet pile walls, controlling ground water with jet grouting and controlling Kifisos River waters with embankments and rerouting pipes.